North European ports stay stretched as Hamburg terminal yard hits 99%
Kuehne+Nagel's latest port update shows mainline vessels waiting one to two days at major North European and UK ports, with Hamburg's CTH terminal critically congested and Bremerhaven's yard at 89%.
Kuehne+Nagel's weekly port operations update for 18–24 November, which uses seven-day averages of mainline vessel waiting times, shows congestion persisting across North Europe. London Gateway had the longest wait at about 2.0 days, followed by Wilhelmshaven and Southampton at about 1.5 days and Hamburg at about 1.4 days.
Yard capacity is the main pressure point in Germany. In Hamburg, occupancy at the CTA terminal eased to 77%, but CTH was described as critically congested at 99%, with reefer capacity exceeded. Bremerhaven's yard remained high at 89%, with space for dangerous goods and out-of-gauge cargo increasingly tight, and Wilhelmshaven's yard density was about 80%.
In Rotterdam, vessels waited about 1.27 days on average. Yard occupancy was around 90% at MVII and 70% at ECT, while barge and feeder connections faced delays of 12 to 36 hours. Antwerp averaged about 1.19 days, with truck turnaround times of 23–25 minutes, and Le Havre about one day, with reefer utilisation at 87%.
What it means for shippers: waits of one to two days are manageable, but full yards slow container pick-up and hinterland moves. Importers using Hamburg and Bremerhaven, particularly for reefer, dangerous-goods or oversized cargo, should allow extra time, and those relying on barge or feeder services out of Rotterdam should plan for delays of up to a day and a half.